Architectural RFP: How to Structure and Efficiently Prepare VOB-Compliant Bill of Quantities

8. July 2026

For architects, a request for proposals is much more than just a formal step in the planning process. It plays a decisive role in determining how accurately bids can be compared, how smoothly the implementation proceeds, and whether projects remain within budget.

Especially in the context of the VOB, it quickly becomes clear how important a clear structure, unambiguous scope of work, and accurately determined quantities are. Without this foundation, uncertainties, follow-up questions, and—in the worst case—costly change orders arise. A well-thought-out request for proposals is therefore not only mandatory but also a key tool for ensuring quality, control, and efficiency throughout the entire construction project.

At NOVA AVA, we focus specifically on these real-world requirements. We explain what matters most in a structured bid process in accordance with VOB and how architects can structure their processes to ensure that Bill of Quantities are created in a way that is transparent, reliable, and efficient.

In this article, you’ll learn how to structure a bid in accordance with VOB, avoid common mistakes, and work more efficiently with clear processes. The goal is to provide you with practical guidance that will help you create your Bill of Quantities in a reliable, understandable, and professional manner.

What does a call for bids for architects under the VOB entail?

In the request for proposals, the planned construction work is described and broken down in such a way that companies can use it to develop a bid. Architects thus translate the current state of planning into a cost-estimable scope of work.

In the “Buildings and Interiors” service category, the preparation of service descriptions with Bill of Quantities organized by service area is a core service of HOAI Service Phase 6. However, the specific tasks required for a given project always depend on the individual terms of the engagement.

The VOB is particularly important for construction project bids. It consists of three parts:

VOB/A: It contains provisions governing the awarding of construction contracts. For public contracting authorities, it is also crucial to determine which section of the VOB/A and which other public procurement regulations apply to the specific procedure.

VOB/B: It governs the general terms and conditions for the performance of construction work. It does not automatically apply to private construction contracts. It must be expressly agreed upon as part of the contract to be valid.

VOB/C: It contains the General Technical Contract Conditions for Construction Work. These include general rules as well as trade-specific ATVs for various areas of work.

The commonly used term “VOB-compliant Bill of Quantities” refers, in practice, to a Bill of Quantities that takes the relevant requirements into account. No blanket guarantee can be inferred from this. The specific scope of work, the procurement process, the contract documents, and the current stage of planning are always decisive factors.

Why a Structured Request for Proposals Is Crucial

A well-drafted request for proposals ensures that all bidders calculate their bids based on as similar a scope of work as possible. To achieve this, the scope of the contract must be described clearly, completely, and in a way that is understood in the same sense by the companies being solicited.

The Bill of Quantities will not only serve as the basis for preparing a bid later on. It will also guide the project through subsequent phases:

  • Quotes are compared based on the items listed.
  • Services are contracted based on the Bill of Quantities.
  • Changes are assigned to the original items.
  • Quantities shipped are recorded.
  • Interim invoices and final invoices are reviewed.
  • Costs can be compared with the plan and the order.

If services are missing or wording remains ambiguous, uncertainty will persist throughout the remainder of the project.

However, just because a Bill of Quantities is particularly long doesn’t automatically mean it’s a good one. What matters most is a clear structure, unambiguous items, correct quantities, and consistent documentation.

The Basics of a VOB-Compliant Request for Proposals

A key requirement for service specifications is that the service be described as clearly and comprehensively as possible. All companies should be able to interpret the description in the same way and prepare bids that are comparable with one another.

This gives rise to several guidelines for the call for proposals.

Describe services clearly and completely

A work item must clearly specify what is to be manufactured, delivered, installed, or processed. Equally important are the required quality, the relevant dimensions, the installation location, and any special design requirements.

Information that is essential for the cost estimate must not be clarified only during the execution phase.

Do not expose bidders to unforeseeable risks

Companies need a solid basis for their pricing. Unusual conditions or risks that the client can influence or describe should not be passed on to the contractor across the board.

Issue a product-neutral request for proposals

In public solicitations, services should generally be described in a product-neutral manner. The description therefore focuses on technical, functional, and quality requirements.

Brands or specific makes must not automatically be specified as the sole requirement. If, in exceptional cases, a specific designation is necessary, the requirements under public procurement law for the respective procedure must be observed.

Take VOB/C and ATV into account

The VOB/C contains technical contract terms for individual trades. Among other things, it addresses issues related to execution, billing, ancillary services, and special services.

According to the applicable provisions, ancillary services are generally considered part of the contractual scope of services, even if they are not listed as separate items. Special services, on the other hand, are included in the scope of services only if they are described separately.

When drafting the Bill of Quantities, it is therefore necessary to determine which services are already covered by the applicable ATV (General Technical Contract Conditions for Construction Work) and which services must be explicitly described.

Coordinate all documents

The Bill of Quantities, plans, construction specifications, and contract terms must not contradict one another. Differing dimensions or quality requirements do not provide any additional certainty. Rather, they lead to confusion as to which information should be considered authoritative.

Step by Step Toward a VOB-Compliant Request for Proposals

A structured request for proposals does not begin with drafting the first item. First, the status of planning, the scope of work, and the award structure must be sufficiently clarified.

1. Clearly define the project and scope of work

Before drafting the Bill of Quantities, it should be determined which services will be put out to bid and how they will be divided into award units or lots.

These include, in particular:

  • The Demarcation of Trades
  • the assignment of services to award units
  • the interfaces between the companies involved
  • the current status of planning
  • the specified materials and grades
  • site conditions
  • the necessary preliminary work
  • the planned implementation periods
  • the available plans and details

Interfaces deserve special attention. For example, if it is not clearly specified which trade is responsible for creating an opening, substructure, waterproofing, or connection, a service may be counted twice or not at all.

The cost estimate should also be compared with the request for proposals. This makes it possible to verify whether all planned scope of work is included and whether the quantities and quality specifications in the request for proposals still align with the project’s economic objectives.

2. Define the structure of the Bill of Quantities

A Bill of Quantities is not simply a disjointed collection of individual items. It requires a hierarchy that is appropriate for the project and the intended contract award.

A possible outline includes:

  • Award Unit or Lot
  • Service Area
  • Title
  • Subtitles
  • Service Items

The Bill of Quantities is supplemented by the construction specifications, preliminary remarks, and required attachments.

The construction specifications provide the overall context of the project. They may include information about the construction site, the building, logistics, and general conditions for execution.

Preliminary notes summarize requirements that apply to a specific area of performance or multiple positions. However, they should not be used to hide critical performance components in a hard-to-find location.

Service items describe the specific individual services to be costed, including quantity and unit.

Sequence numbers ensure that items can be uniquely identified. A consistent sequence structure is particularly important for GAEB data exchange, bid evaluation, order placement, and subsequent billing.

3. Clearly define service items

A well-structured bill of materials answers all the questions that are essential for a realistic cost estimate.

Depending on the service, these may include:

  • Nature and Scope of the Service
  • Material and Quality
  • Dimensions and Coating Thicknesses
  • Substrate or installation conditions
  • Installation Location
  • Processing Method
  • Surface Requirements
  • special technical features
  • Quantity and Unit of Measure

The short description is primarily intended to provide a quick overview. The long description contains the complete service description. A brief short description should therefore not be confused with a sufficiently detailed item.

A phrase such as “Painting a wall, complete” is ambiguous. For example, it lacks details regarding the substrate, preparation, coating system, number of application steps, required surface quality, and installation location.

A more specific description could clarify that an existing plastered interior wall is to be prepared, primed, and coated with a specific coating system to a defined standard of coverage. The specific details required depend on the scope of work and the relevant technical regulations.

Use Placeholder Text Wisely

Tender documents from STLB Bau, BKI, sirAdos, or other databases can make the work easier. They provide technically structured text templates and help ensure that recurring construction services are described consistently.

Nevertheless, the texts must be tailored to the specific project. A standard text does not take into account the specific installation situation, interfaces, design details, or contractual requirements of the individual construction project.

NOVA AVA allows users to utilize various bid document templates. For example, BKI work items and sirAdos construction data can be imported via the GAEB XML interface and used as the basis for Bills of Quantities.

Make Strategic Use of Special Line Items

Requirement items, alternative items, and allowance items serve different purposes. If they are used ambiguously or too frequently, they complicate the evaluation of bids and the subsequent awarding of contracts.

A “contingency item” should only be used if the service has not yet been definitively determined at the time of the request for proposals but could realistically be required. “Alternative items” are used to compare different implementation options. “Surcharge items” supplement a basic service by adding a clearly defined additional cost.

In any case, it must be clear when and under what conditions each position is executed.

4. Determine quantities correctly

Quantities link planning, cost estimation, and the Bill of Quantities. If they do not match the current status of planning, the bid totals derived from them also lose their significance.

A transparent quantity calculation takes the following into account:

  • the current plans
  • the relevant billing rules
  • the correct unit of measure
  • Openings and Recesses
  • Molded Parts and Special Components
  • Assignments to Rooms, Floors, or Areas
  • Changes to the Planning Status

Quantities should not be documented solely as final values. The calculation process must also remain traceable. This facilitates internal audits and subsequent adjustments.

Manual transfers are particularly problematic. If quantities are first calculated in spreadsheets and then transferred individually to the Bill of Quantities, multiple versions of the data are created. When changes are made to the plans, it is not always clear which file is the most current.

Digital processes can reduce this need for duplicate data entry. Nevertheless, quantities determined automatically or based on models must be verified by subject matter experts.

5. Compile the complete set of bid documents

The Bill of Quantities is only one part of the bidding documents. Companies need all the information relevant to preparing and calculating their bid.

Depending on the process and project, these may include:

  • Request for Proposals
  • Application Requirements
  • Terms and Conditions
  • Building Specifications
  • Bill of Quantities
  • Plans and Detailed Drawings
  • Schedule Information
  • Additional Technical Contract Terms
  • Forms
  • Required explanations and supporting documentation
  • Guidelines for Submitting a Bid

Before publication, all documents should be reviewed together one more time. It is particularly important to ensure that all documents have the same revision status, unambiguous file names, and consistent information.

If any relevant information changes after the bidding process has begun, the change must be documented in a transparent manner and made available to all affected bidders in the same way.

Common Mistakes in RFP Responses and How to Avoid Them

Many problems do not arise from a single incorrect position. Often, several minor ambiguities occur simultaneously.

The call for proposals starts too early

If the planning is not yet sufficiently developed, quantities, details, and binding quality specifications are missing.

Better: Before the bidding process begins, establish a defined planning status and document any outstanding decisions.

Trades are not clearly defined

Unclear responsibilities lead to gaps or duplication of effort.

Better: Review work across all trades and define responsibilities for connections, preliminary work, and ancillary tasks.

Policy statements remain too general

Terms such as “complete,” “proper,” or “as needed” are no substitute for a quantifiable description.

Better: Specify the type, quality, scope, and terms of performance in concrete terms.

Old Bill of Quantities are copied without being reviewed

Templates may contain outdated requirements or inappropriate items.

Better: Review each adopted item for its relevance to the project, technical relevance, and actual necessity.

The plans and the Bill of Quantities contradict each other

Discrepancies in the information provided lead to follow-up questions and room for interpretation.

Better: Before publication, conduct a systematic comparison of the BOQ, plans, and specifications.

Quantities are not traceable

Incorrect or outdated quantities distort the total amount of the quote.

Better: Document the basis for calculations and update quantities following changes to the plan.

Files are transferred manually

Word, Excel, PDF, and various standalone solutions create duplicate data sets.

Better: Manage Bill of Quantities, quantities, and bid data within a single, end-to-end AVA process whenever possible.

Digital Tools for Tendering in Architectural Firms

AVA software streamlines the process from the creation of the Bill of Quantities to the evaluation of bids. It can help standardize recurring tasks and ensure that information is reused throughout the process.

Key features include:

  • Structure of Bill of Quantities
  • Management of Titles and Positions
  • Using Your Own Templates
  • Incorporation of Professional Bid Documents
  • Maintaining Quantities and Estimated Prices
  • GAEB Import and Export
  • Export as Excel or PDF
  • Digital Provision of Documents
  • Importing Incoming Quote Data
  • Preparation of a Price Comparison Table
  • Further Processing for Contract Award and Billing

NOVA AVA maps these workflow steps in a cloud-based application. Bill of Quantities can be created in a browser, exchanged via GAEB, and then reused for tendering, bid comparison, and contract award.

The software thus supports a structured process. It is still up to the responsible planners to assess whether the Bill of Quantities is complete and technically suitable for the project in question.

Tendering According to VOB and BIM: How Do They Fit Together?

BIM models can provide component information and quantities that serve as the basis for cost planning and bidding. This eliminates the need to re-enter certain information from scratch for each step of the process.

A prerequisite is a model whose information content is appropriate for the intended use. In addition, components must be clearly classified, quantity rules must be defined, and relevant properties must be maintained.

A possible workflow includes:

  1. Apply IFC Model
  2. Select Components by Properties and Filters
  3. Verify quantities from a technical standpoint
  4. Assign Components to Cost Estimates or BOQ Line Items
  5. Add non-modeled content to the Bill of Quantities

A BIM model does not automatically generate a complete Bill of Quantities. Site setup, special construction conditions, ancillary services, special services, and contractual requirements are often not fully included in the model.

With the BIM add-on from NOVA AVA, IFC models can be used for model-based quantity and cost planning. Building components can be filtered and linked to costs or line items. Technical review remains an indispensable part of the process here as well.

Conclusion: When it comes to architectural design competitions, structure trumps effort

When people talk about “architectural bid documents,” they often think primarily of drafting individual line item descriptions. In fact, a good bid document process begins much earlier. It requires a sufficiently advanced stage of planning, clearly defined scope of work, and verifiable quantities.

Quality does not result from texts that are as extensive as possible. What matters most are clear positions, an appropriate BOQ structure, coordinated planning documents, and a final review of all contract award documents.

Digital tools can make this process more efficient and consistent. They reduce manual data entry, create centralized data repositories, and enable the reuse of tender data for bid comparison, award, and billing.

The responsibility for ensuring that the scope of work is complete and appropriate for the specific project remains with the experts involved.

Creating Structured Bill of Quantities with NOVA AVA

NOVA AVA supports architectural firms in creating and editing Bill of Quantities, in GAEB data exchange, and in both traditional and digital bidding processes.

The data can then be reused for price comparisons, contract awarding, contract management, and billing. Since NOVA AVA is browser-based, project participants can access approved content from anywhere.